A A Estates Pvt Ltd
RERA delivery track record · complaints · project delays
NAME:A A ESTATES
F15/100
Poor track record
Tracking 4 projects — 0 delivered, 4 still active. 4 of 4 (100%) ran late.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
4
Completed
0
Delayed
4 (100%)
Late or overdue
Avg delay
—
On finished projects
On-time rate
—
Of completed projects
Extension rate
25%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800008635 Mumbai Suburban · MH | Mumbai Suburban MH | 19 Aug 2017 | 31 Dec 2018 | Overdue | 54 mo overdue |
Redevelopment of bldg 5 and 6 Samrat and Pulkit CHS LTD CTS no 195 pt D N Ngr Mhada layout Andheri W P51800005826 Mumbai Suburban · MH | Mumbai Suburban MH | 14 Aug 2017 | 30 Dec 2022 | Overdue | 42 mo overdue |
P51800004643 Mumbai Suburban · MH | Mumbai Suburban MH | 9 Aug 2017 | 28 Aug 2023 | Overdue | 34 mo overdue |
P51800004918 Mumbai Suburban · MH | Mumbai Suburban MH | 9 Aug 2017 | 28 Aug 2023 | Overdue | 34 mo overdue |