ABHIGNA ENTERPRISES
NAME:ABHIGNA ENTERPRISES
F0/100
Poor track record
Tracking 2 projects — 1 delivered, 1 still active. 2 of 2 (100%) ran late by an average of 42 months. Limited history — read the project list before drawing conclusions.
This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.
Delivery breakdown
How this builder's 2 tracked projects are split by outcome.
Key numbers
Total projects
2
Active
1
Completed
1
Delayed
2 (100%)
Late or overdue
Avg delay
41.5 mo
Worst: 41.5 mo
On-time rate
0%
Of completed projects
Extension rate
100%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (2)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800007245 Mumbai Suburban · MH | Mumbai Suburban MH | 17 Aug 2017 | 31 Dec 2019 | Completed | 42 mo delay |
P51800032546 Mumbai Suburban · MH | Mumbai Suburban MH | 10 Jan 2022 | 30 Sept 2024 | Overdue | 12 mo overdue |