AJAY MALSHI DEDHIA
RERA delivery track record · complaints · project delays
NAME:AJAY MALSHI DEDHIA
C63/100
Mixed track record
Tracking 3 projects — 1 delivered, 2 still active. 2 of 3 (67%) ran late.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
2
Completed
1
Delayed
2 (67%)
Late or overdue
Avg delay
0 mo
On finished projects
On-time rate
100%
Of completed projects
Extension rate
67%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800008340 Mumbai Suburban · MH | Mumbai Suburban MH | 18 Aug 2017 | 31 Mar 2018 | Overdue | 18 mo overdue |
P51800029561 Mumbai Suburban · MH | Mumbai Suburban MH | 4 Jun 2021 | 31 Dec 2022 | Overdue | 6 mo overdue |
P51800031906 Mumbai Suburban · MH | Mumbai Suburban MH | 22 Nov 2021 | 30 Jun 2023 | Completed | On track |