ALAG PROPERTY CONSTRUCTIONS PVT. LTD.

RERA delivery track record · complaints · project delays

NAME:ALAG PROPERTY CONSTRUCTIONS

Poor track record

Tracking 4 projects — 2 delivered, 2 still active. 3 of 4 (75%) ran late by an average of 9 months.

Delivery breakdown

How this builder's 4 tracked projects are split by outcome.

2 Delivered late1 Overdue1 In progress

Key numbers

Total projects

4

Active

2

Completed

2

Delayed

3 (75%)

Late or overdue

Avg delay

9 mo

Worst: 12 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (4)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800003162
Mumbai Suburban · MH
Mumbai Suburban
MH
4 Aug 201730 Jun 2021Overdue42 mo overdue
P51800006661
Mumbai Suburban · MH
Mumbai Suburban
MH
16 Aug 201731 Dec 2017Completed6 mo delay
P51800018925
Mumbai Suburban · MH
Mumbai Suburban
MH
17 Dec 201830 Jun 2021Completed12 mo delay
P51800020773
Mumbai Suburban · MH
Mumbai Suburban
MH
9 May 201930 Jun 2024In progressOn track