ALPINE INFRAPROJECTS PVT LTD

NAME:ALPINE INFRAPROJECTS PVT LTD

Weak track record

Tracking 4 projects — 2 delivered, 2 still active. 2 of 4 (50%) ran late by an average of 3 months.

Delivery breakdown

How this builder's 4 tracked projects are split by outcome.

1 Delivered on time1 Delivered late1 Overdue1 In progress

Key numbers

Total projects

4

Active

2

Completed

2

Delayed

2 (50%)

Late or overdue

Avg delay

3 mo

Worst: 6 mo

On-time rate

50%

Of completed projects

Extension rate

50%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (4)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
AIG ROYAL ( PHASE-2)
UPRERAPRJ958972
Gautam Buddha Nagar
UP
3 Feb 202020 Jun 2023Overdue30 mo overdue
AIG ROYAL (PHASE 1)
UPRERAPRJ17394
UP
20 Aug 201820 Jun 2023Completed6 mo delay
AIG IN ROYAL ( PHASE 3)
UPRERAPRJ902517
UP
17 Dec 202120 Jun 2023CompletedOn track
AIGIN ROYAL PHASE 4
UPRERAPRJ309036
Gautam Buddha Nagar
UP
30 Jun 202326 Mar 2028In progressOn track