AURA BUILDWELL PVT. LTD.

NAME:AURA BUILDWELL PVT. LTD.

Poor track record

Tracking 2 projects — 1 delivered, 1 still active. 2 of 2 (100%) ran late by an average of 6 months. Limited history — read the project list before drawing conclusions.

This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.

Delivery breakdown

How this builder's 2 tracked projects are split by outcome.

1 Delivered late1 Overdue

Key numbers

Total projects

2

Active

1

Completed

1

Delayed

2 (100%)

Late or overdue

Avg delay

6 mo

Worst: 6 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (2)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
FORESTE, PHASE-I (COMPRISING TOWERS T1, T2, T3,T8,
UPRERAPRJ3680
Gautam Buddha Nagar
UP
28 Jul 201731 Dec 2020Overdue60 mo overdue
FORESTE, PHASE-II (COMPRISING TOWERS T4, T5,T9)
UPRERAPRJ3777
UP
28 Jul 201731 Dec 2021Completed6 mo delay