BESTECH INDIA PVT LTD
NAME:BESTECH INDIA
C52/100
Mixed track record
Tracking 5 projects — 0 delivered, 5 still active. 3 of 5 (60%) ran late.
Delivery breakdown
How this builder's 5 tracked projects are split by outcome.
Key numbers
Total projects
5
Active
5
Completed
0
Delayed
3 (60%)
Late or overdue
Avg delay
—
On finished projects
On-time rate
—
Of completed projects
Extension rate
0%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (5)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
RERA-GRG-304-2019 Gurgaon · HR | Gurgaon HR | 9 Dec 2019 | 31 Mar 2025 | Overdue | 15 mo overdue |
RERA-GRG-1355-2023 Gurgaon · HR | Gurgaon HR | 24 Jul 2023 | 16 Sept 2026 | In progress | On track |
RERA-GRG-1362-2023 Gurgaon · HR | Gurgaon HR | 3 Jul 2023 | 7 Oct 2026 | In progress | On track |
RERA-GRG-756-2020 Gurgaon · HR | Gurgaon HR | 18 Dec 2020 | 27 Jul 2025 | Overdue | 11 mo overdue |
RERA-GRG-397-2019 Gurgaon · HR | Gurgaon HR | 28 Aug 2017 | 30 Sept 2024 | Overdue | 21 mo overdue |