BHOLENATH DEVELOPERS LTD.

RERA delivery track record · complaints · project delays

NAME:BHOLENATH DEVELOPERS

Poor track record

Tracking 4 projects — 4 delivered, 0 still active. 3 of 4 (75%) ran late by an average of 26 months.

Delivery breakdown

How this builder's 4 tracked projects are split by outcome.

1 Delivered on time3 Delivered late

Key numbers

Total projects

4

Active

0

Completed

4

Delayed

3 (75%)

Late or overdue

Avg delay

26 mo

Worst: 62 mo

On-time rate

25%

Of completed projects

Extension rate

75%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (4)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800004835
Mumbai Suburban · MH
Mumbai Suburban
MH
9 Aug 201714 Nov 2022Completed12 mo delay
P51800009179
Mumbai Suburban · MH
Mumbai Suburban
MH
19 Aug 201731 Oct 2018Completed62 mo delay
P51800000759
Mumbai Suburban · MH
Mumbai Suburban
MH
23 Jul 201730 Jun 2018Completed30 mo delay
P51800002227
Mumbai Suburban · MH
Mumbai Suburban
MH
31 Jul 201731 Mar 2018CompletedOn track