← Back to search

BHUTANI GROUP

NAME:BHUTANI GROUP

Poor track record

Tracking 2 projects — 2 delivered, 0 still active. 2 of 2 (100%) ran late by an average of 18 months. Limited history — read the project list before drawing conclusions.

This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.

Delivery breakdown

How this builder's 2 tracked projects are split by outcome.

2 Delivered late

Key numbers

Total projects

2

Active

0

Completed

2

Delayed

2 (100%)

Late or overdue

Avg delay

17.9 mo

Worst: 18 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (2)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
Alphathum PH-III
UPRERAPRJ10097
UP
15 Aug 20171 Feb 2021Completed18 mo delay
Alphathum Phase - IV
UPRERAPRJ10115
UP
15 Aug 20171 Mar 2021Completed18 mo delay