BPTP LIMITED

NAME:BPTP

Mixed track record

Tracking 15 projects — 0 delivered, 15 still active. 9 of 15 (60%) ran late.

Delivery breakdown

How this builder's 15 tracked projects are split by outcome.

9 Overdue6 In progress

Key numbers

Total projects

15

Active

15

Completed

0

Delayed

9 (60%)

Late or overdue

Avg delay

On finished projects

On-time rate

Of completed projects

Extension rate

0%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (15)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
RERA-GRG-1817-2024
Gurgaon · HR
Gurgaon
HR
1 May 202527 Nov 2029In progressOn track
RERA-PKL-591-2019
Faridabad · HR
Faridabad
HR
16 Oct 201712 Oct 2021Overdue56 mo overdue
RERA-PKL-1914-2025
Faridabad · HR
Faridabad
HR
31 Mar 2033In progressOn track
RERA-GRG-2009-2025
Gurgaon · HR
Gurgaon
HR
19 Sept 202531 Oct 2032In progressOn track
RERA-GRG-1830-2024
Gurgaon · HR
Gurgaon
HR
5 Feb 202514 Dec 2031In progressOn track
RERA-GRG-2136-2025
Gurgaon · HR
Gurgaon
HR
5 Jun 202631 Dec 2032In progressOn track
RERA-GRG-1959-2025
Gurgaon · HR
Gurgaon
HR
27 Jun 202531 Jul 2032In progressOn track
RERA-GRG-660-2020
Gurgaon · HR
Gurgaon
HR
3 Jan 201831 Aug 2019Overdue82 mo overdue
RERA-GRG-443-2019
Gurgaon · HR
Gurgaon
HR
13 Oct 201712 Oct 2020Overdue68 mo overdue
RERA-GRG-662-2020
Gurgaon · HR
Gurgaon
HR
17 Nov 201731 May 2018Overdue97 mo overdue
RERA-GRG-669-2020
Gurgaon · HR
Gurgaon
HR
13 Oct 201711 Apr 2024Overdue26 mo overdue
RERA-PKL-870-2020
Faridabad · HR
Faridabad
HR
31 Aug 2025Overdue10 mo overdue
RERA-PKL-590-2019
Faridabad · HR
Faridabad
HR
13 Oct 201731 Jul 2022Overdue47 mo overdue
RERA-PKL-1055-2022
Faridabad · HR
Faridabad
HR
30 Jun 2024Overdue24 mo overdue
RERA-PKL-650-2019
Faridabad · HR
Faridabad
HR
30 Sept 2025Overdue9 mo overdue