Chaitanya Developers
RERA delivery track record · complaints · project delays
NAME:CHAITANYA DEVELOPERS
D35/100
Weak track record
Tracking 6 projects — 6 delivered, 0 still active. 3 of 6 (50%) ran late by an average of 10 months.
Delivery breakdown
How this builder's 6 tracked projects are split by outcome.
Key numbers
Total projects
6
Active
0
Completed
6
Delayed
3 (50%)
Late or overdue
Avg delay
10.2 mo
Worst: 46.4 mo
On-time rate
50%
Of completed projects
Extension rate
50%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (6)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51900034202 Mumbai City · MH | Mumbai City MH | 25 Mar 2022 | 31 Dec 2024 | Completed | On track |
P51800007842 Mumbai Suburban · MH | Mumbai Suburban MH | 18 Aug 2017 | 9 Mar 2022 | Completed | 12 mo delay |
P51800024570 Mumbai Suburban · MH | Mumbai Suburban MH | 24 Feb 2020 | 30 Jun 2023 | Completed | On track |
P51800029553 Mumbai Suburban · MH | Mumbai Suburban MH | 4 Jun 2021 | 31 May 2024 | Completed | 3 mo delay |
P51800035185 Mumbai Suburban · MH | Mumbai Suburban MH | 10 May 2022 | 31 Dec 2024 | Completed | On track |
P52100003910 Pune · MH | Pune MH | 6 Aug 2017 | 15 Feb 2021 | Completed | 46 mo delay |