Charms Developers
NAME:Charms Developers
F26/100
Poor track record
Tracking 3 projects — 2 delivered, 1 still active. 2 of 3 (67%) ran late by an average of 12 months.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
1
Completed
2
Delayed
2 (67%)
Late or overdue
Avg delay
12 mo
Worst: 24 mo
On-time rate
50%
Of completed projects
Extension rate
67%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| CHARMS HEIGHTS PHASE-I B1-B4 P51700002055 | Thane MH | 31 Jul 2017 | 31 Mar 2018 | Completed | On track |
| CHARMS HEIGHTS PHASE-III B2-B3 P51700002081 | Thane MH | 31 Jul 2017 | 30 Jun 2022 | Overdue | 6 mo overdue |
| CHARMS HEIGHTS PHASE-II A1-A2 P51700002670 | Thane MH | 2 Aug 2017 | 31 Mar 2019 | Completed | 24 mo delay |