DEVSAI CONSTRUCTION PRIVATE LIMITED

NAME:DEVSAI CONSTRUCTION PRIVATE LIMITED

Poor track record

Tracking 2 projects — 2 delivered, 0 still active. 2 of 2 (100%) ran late by an average of 16 months. Limited history — read the project list before drawing conclusions.

This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.

Delivery breakdown

How this builder's 2 tracked projects are split by outcome.

2 Delivered late

Key numbers

Total projects

2

Active

0

Completed

2

Delayed

2 (100%)

Late or overdue

Avg delay

16.5 mo

Worst: 26.9 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (2)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
SPORTSHOME
UPRERAPRJ6815
UP
31 Jul 201731 Mar 2020Completed27 mo delay
SPORTSHOME PHASE II
UPRERAPRJ743918
UP
13 Apr 201931 Dec 2023Completed6 mo delay