Dhanlaxmi Builders And Developers
NAME:DHANLAXMI BUILDERS AND DEVELOPERS
F0/100
Poor track record
Tracking 3 projects — 1 delivered, 2 still active. 3 of 3 (100%) ran late by an average of 12 months.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
2
Completed
1
Delayed
3 (100%)
Late or overdue
Avg delay
12 mo
Worst: 12 mo
On-time rate
0%
Of completed projects
Extension rate
100%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P52100008858 Pune · MH | Pune MH | 19 Aug 2017 | 26 Jan 2019 | Overdue | 54 mo overdue |
P52100011889 Pune · MH | Pune MH | 31 Aug 2017 | 26 Jan 2019 | Completed | 12 mo delay |
P52100010450 Pune · MH | Pune MH | 27 Aug 2017 | 1 May 2019 | Overdue | 68 mo overdue |