EARTH INFRASTRUCTURES LIMITED
NAME:EARTH INFRASTRUCTURES LIMITED
F0/100
Poor track record
Tracking 3 projects — 1 delivered, 2 still active. 3 of 3 (100%) ran late by an average of 6 months.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
2
Completed
1
Delayed
3 (100%)
Late or overdue
Avg delay
6 mo
Worst: 6 mo
On-time rate
0%
Of completed projects
Extension rate
67%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| Earth Sapphire Court UPRERAPRJ9887 | Gautam Buddha Nagar UP | 24 Oct 2017 | 31 Dec 2018 | Overdue | 90 mo overdue |
| Earth Techone UPRERAPRJ9979 | Gautam Buddha Nagar UP | 25 Oct 2017 | 30 Jun 2020 | Overdue | 66 mo overdue |
| Earth Towne UPRERAPRJ10012 | UP | 24 Oct 2017 | 31 Dec 2021 | Completed | 6 mo delay |