ELEGANT INFRACON PVT LTD

NAME:ELEGANT INFRACON PVT LTD

Poor track record

Tracking 5 projects — 5 delivered, 0 still active. 5 of 5 (100%) ran late by an average of 53 months.

Delivery breakdown

How this builder's 5 tracked projects are split by outcome.

5 Delivered late

Key numbers

Total projects

5

Active

0

Completed

5

Delayed

5 (100%)

Late or overdue

Avg delay

52.6 mo

Worst: 66.6 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (5)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
ELEGANT SPLENDOUR PHASE-1
UPRERAPRJ10243
UP
23 Aug 20173 Sept 2019Completed52 mo delay
ELEGANT SPLENDOUR PHASE-3
UPRERAPRJ10279
UP
13 Aug 20171 Mar 2021Completed58 mo delay
ELEGANT VILLE PHASE-4
UPRERAPRJ10234
UP
19 Aug 201731 Jul 2019Completed61 mo delay
ELEGANT VILLE PHASE-1
UPRERAPRJ10120
UP
14 Aug 201722 Jul 2022Completed26 mo delay
ELEGANT VILLE PHASE-3
UPRERAPRJ10224
UP
14 Aug 201727 Feb 2019Completed67 mo delay