GAURSONS HI-TECH INFRASTRUCTURE PRIVATE LIMITED

NAME:GAURSONS HI-TECH INFRASTRUCTURE PRIVATE LIMITED

Poor track record

Tracking 3 projects — 2 delivered, 1 still active. 3 of 3 (100%) ran late by an average of 6 months.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

2 Delivered late1 Overdue

Key numbers

Total projects

3

Active

1

Completed

2

Delayed

3 (100%)

Late or overdue

Avg delay

6 mo

Worst: 6 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
Gaur City Center
UPRERAPRJ4780
UP
31 Jul 201731 Jan 2024Completed6 mo delay
Gaur Mulberry Mansions - FH-03
UPRERAPRJ4897
Gautam Buddha Nagar
UP
31 Jul 201731 Oct 2022Overdue44 mo overdue
Gaur City Mall
UPRERAPRJ6934
UP
31 Jul 201731 Dec 2023Completed6 mo delay