GAYATRI BUILDERS
NAME:GAYATRI BUILDERS
D35/100
Weak track record
Tracking 2 projects — 2 delivered, 0 still active. 1 of 2 (50%) ran late by an average of 17 months. Limited history — read the project list before drawing conclusions.
This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.
Delivery breakdown
How this builder's 2 tracked projects are split by outcome.
Key numbers
Total projects
2
Active
0
Completed
2
Delayed
1 (50%)
Late or overdue
Avg delay
16.5 mo
Worst: 33 mo
On-time rate
50%
Of completed projects
Extension rate
50%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (2)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| GAYATRI KRUPA P51700007229 | Thane MH | 17 Aug 2017 | 30 Dec 2022 | Completed | 33 mo delay |
| GAYATRI DHAM P51700003573 | Thane MH | 5 Aug 2017 | 31 Mar 2018 | Completed | On track |