GULSHAN HOMES AND INFRASTRUCTURE PRIVATE LIMITED

NAME:GULSHAN HOMES AND INFRASTRUCTURE PRIVATE LIMITED

Weak track record

Tracking 2 projects — 2 delivered, 0 still active. 1 of 2 (50%) ran late by an average of 3 months. Limited history — read the project list before drawing conclusions.

This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.

Delivery breakdown

How this builder's 2 tracked projects are split by outcome.

1 Delivered on time1 Delivered late

Key numbers

Total projects

2

Active

0

Completed

2

Delayed

1 (50%)

Late or overdue

Avg delay

3 mo

Worst: 6 mo

On-time rate

50%

Of completed projects

Extension rate

50%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (2)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
Gulshan Botnia
UPRERAPRJ5857
UP
31 Jul 201731 Aug 2023Completed6 mo delay
GULSHAN IKEBANA -TOWERS L,M,N,O,P & Q
UPRERAPRJ8806
UP
10 Aug 201728 Dec 2016CompletedOn track