H.K.PUJARA BUILDERS
RERA delivery track record · complaints · project delays
NAME:H K PUJARA BUILDERS
C52/100
Mixed track record
Tracking 3 projects — 3 delivered, 0 still active. 1 of 3 (33%) ran late by an average of 12 months.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
0
Completed
3
Delayed
1 (33%)
Late or overdue
Avg delay
12 mo
Worst: 36 mo
On-time rate
67%
Of completed projects
Extension rate
33%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800004540 Mumbai Suburban · MH | Mumbai Suburban MH | 9 Aug 2017 | 31 Dec 2018 | Completed | On track |
P51800004317 Mumbai Suburban · MH | Mumbai Suburban MH | 9 Aug 2017 | 31 Mar 2019 | Completed | On track |
P51800004626 Mumbai Suburban · MH | Mumbai Suburban MH | 9 Aug 2017 | 30 Dec 2023 | Completed | 36 mo delay |