HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD
RERA delivery track record · complaints · project delays
NAME:HOUSING DEVELOPMENT AND INFRASTRUCTURE
F13/100
Poor track record
Tracking 8 projects — 0 delivered, 8 still active. 8 of 8 (100%) ran late.
Delivery breakdown
How this builder's 8 tracked projects are split by outcome.
Key numbers
Total projects
8
Active
8
Completed
0
Delayed
8 (100%)
Late or overdue
Avg delay
—
On finished projects
On-time rate
—
Of completed projects
Extension rate
38%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (8)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800012577 Mumbai Suburban · MH | Mumbai Suburban MH | 4 Sept 2017 | 31 Dec 2017 | Overdue | 97 mo overdue |
P51800004431 Mumbai Suburban · MH | Mumbai Suburban MH | 9 Aug 2017 | 31 Jan 2021 | Overdue | 65 mo overdue |
P51800010758 Mumbai Suburban · MH | Mumbai Suburban MH | 31 Aug 2017 | 31 Jan 2021 | Overdue | 65 mo overdue |
P51800007809 Mumbai Suburban · MH | Mumbai Suburban MH | 18 Aug 2017 | 30 Nov 2020 | Overdue | 67 mo overdue |
P51800009742 Mumbai Suburban · MH | Mumbai Suburban MH | 22 Aug 2017 | 30 Oct 2022 | Overdue | 44 mo overdue |
P51800007283 Mumbai Suburban · MH | Mumbai Suburban MH | 17 Aug 2017 | 30 Dec 2020 | Overdue | 66 mo overdue |
P51800016598 Mumbai Suburban · MH | Mumbai Suburban MH | 25 May 2018 | 31 Dec 2018 | Overdue | 78 mo overdue |
P51800007814 Mumbai Suburban · MH | Mumbai Suburban MH | 18 Aug 2017 | 31 Oct 2018 | Overdue | 80 mo overdue |