Indiabulls Infraestate Limited
NAME:Indiabulls Infraestate Limited
A100/100
Strong track record
Tracking 4 projects — 4 delivered, 0 still active. No delays recorded so far.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
0
Completed
4
Delayed
0 (0%)
Late or overdue
Avg delay
0 mo
On finished projects
On-time rate
100%
Of completed projects
Extension rate
0%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| Indiabulls Blu Tower B P51900000473 | Mumbai City MH | 18 Jul 2017 | 30 Dec 2021 | Completed | On track |
| Indiabulls Blu Tower A P51900000469 | Mumbai City MH | 18 Jul 2017 | 30 Dec 2021 | Completed | On track |
| Indiabulls Blu Tower C P51900000843 | Mumbai City MH | 23 Jul 2017 | 30 Dec 2021 | Completed | On track |
| Indiabulls Blu Tower D P51900000871 | Mumbai City MH | 23 Jul 2017 | 30 Jun 2022 | Completed | On track |