JE AND VEE INFRASTRUCTURE
NAME:JE AND VEE INFRASTRUCTURE
F11/100
Poor track record
Tracking 7 projects — 1 delivered, 6 still active. 3 of 7 (43%) ran late by an average of 8 months.
Delivery breakdown
How this builder's 7 tracked projects are split by outcome.
Key numbers
Total projects
7
Active
6
Completed
1
Delayed
3 (43%)
Late or overdue
Avg delay
8 mo
Worst: 8 mo
On-time rate
0%
Of completed projects
Extension rate
86%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (7)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800017298 Mumbai Suburban · MH | Mumbai Suburban MH | 31 Jul 2018 | 30 Dec 2024 | Overdue | 18 mo overdue |
P51800020431 Mumbai Suburban · MH | Mumbai Suburban MH | 9 Apr 2019 | 31 Dec 2023 | Overdue | 3 mo overdue |
P51800020394 Mumbai Suburban · MH | Mumbai Suburban MH | 9 Apr 2019 | 30 Dec 2023 | Completed | 8 mo delay |
P51800025225 Mumbai Suburban · MH | Mumbai Suburban MH | 23 Mar 2020 | 30 Dec 2024 | In progress | On track |
P51800029730 Mumbai Suburban · MH | Mumbai Suburban MH | 26 Jun 2021 | 31 Dec 2025 | In progress | On track |
P51800030984 Mumbai Suburban · MH | Mumbai Suburban MH | 29 Sept 2021 | 30 Apr 2025 | In progress | On track |
P51800031136 Mumbai Suburban · MH | Mumbai Suburban MH | 5 Oct 2021 | 30 Apr 2025 | In progress | On track |