KABRA ESTATE AND INVESTMENT CONSULTANTS

RERA delivery track record · complaints · project delays

NAME:KABRA ESTATE AND INVESTMENT CONSULTANTS

Good track record

Tracking 4 projects — 4 delivered, 0 still active. 1 of 4 (25%) ran late by an average of 3 months.

Delivery breakdown

How this builder's 4 tracked projects are split by outcome.

3 Delivered on time1 Delivered late

Key numbers

Total projects

4

Active

0

Completed

4

Delayed

1 (25%)

Late or overdue

Avg delay

3 mo

Worst: 12 mo

On-time rate

75%

Of completed projects

Extension rate

25%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (4)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800000684
Mumbai Suburban · MH
Mumbai Suburban
MH
20 Jul 201731 Dec 2018CompletedOn track
P51800000499
Mumbai Suburban · MH
Mumbai Suburban
MH
18 Jul 201731 Dec 2018Completed12 mo delay
P51800016392
Mumbai Suburban · MH
Mumbai Suburban
MH
10 May 201830 Dec 2021CompletedOn track
P51800015963
Mumbai Suburban · MH
Mumbai Suburban
MH
10 Apr 201830 Dec 2023CompletedOn track