KARRM INFRASTRUCTURE PRIVATE LIMITED

RERA delivery track record · complaints · project delays

NAME:KARRM INFRASTRUCTURE

Poor track record

Tracking 5 projects — 0 delivered, 5 still active. 5 of 5 (100%) ran late.

Delivery breakdown

How this builder's 5 tracked projects are split by outcome.

5 Overdue

Key numbers

Total projects

5

Active

5

Completed

0

Delayed

5 (100%)

Late or overdue

Avg delay

On finished projects

On-time rate

Of completed projects

Extension rate

60%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (5)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51700009304
Thane · MH
Thane
MH
22 Aug 201731 Dec 2018Overdue68 mo overdue
P51700007680
Thane · MH
Thane
MH
17 Aug 201730 Dec 2023Overdue30 mo overdue
P51700010325
Thane · MH
Thane
MH
24 Aug 201730 Dec 2022Overdue42 mo overdue
P51700003215
Thane · MH
Thane
MH
5 Aug 201731 May 2019Overdue67 mo overdue
P51700008284
Thane · MH
Thane
MH
18 Aug 201731 May 2019Overdue67 mo overdue