Kaustubh Construction Private Limited
NAME:KAUSTUBH CONSTRUCTION
F18/100
Poor track record
Tracking 5 projects — 4 delivered, 1 still active. 3 of 5 (60%) ran late by an average of 17 months.
Delivery breakdown
How this builder's 5 tracked projects are split by outcome.
Key numbers
Total projects
5
Active
1
Completed
4
Delayed
3 (60%)
Late or overdue
Avg delay
16.5 mo
Worst: 42 mo
On-time rate
25%
Of completed projects
Extension rate
60%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (5)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800007374 Mumbai Suburban · MH | Mumbai Suburban MH | 17 Aug 2017 | 31 Dec 2019 | Completed | 42 mo delay |
P51800006765 Mumbai Suburban · MH | Mumbai Suburban MH | 16 Aug 2017 | 31 Dec 2018 | Completed | 12 mo delay |
P51800046761 Mumbai Suburban · MH | Mumbai Suburban MH | 5 Sept 2022 | 31 Jul 2026 | Completed | On track |
P51800030271 Mumbai Suburban · MH | Mumbai Suburban MH | 10 Aug 2021 | 31 Aug 2024 | Completed | 12 mo delay |
P51800046638 Mumbai Suburban · MH | Mumbai Suburban MH | 25 Aug 2022 | 31 Jul 2026 | In progress | On track |