Kush Buildcon LLP
RERA delivery track record · complaints · project delays
NAME:KUSH BUILDCON
B68/100
Good track record
Tracking 4 projects — 4 delivered, 0 still active. 1 of 4 (25%) ran late by an average of 5 months.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
0
Completed
4
Delayed
1 (25%)
Late or overdue
Avg delay
4.5 mo
Worst: 18 mo
On-time rate
75%
Of completed projects
Extension rate
25%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800007193 Mumbai Suburban · MH | Mumbai Suburban MH | 17 Aug 2017 | 31 Dec 2018 | Completed | On track |
P51800002724 Mumbai Suburban · MH | Mumbai Suburban MH | 4 Aug 2017 | 31 Dec 2017 | Completed | On track |
P51800028906 Mumbai Suburban · MH | Mumbai Suburban MH | 7 Apr 2021 | 30 Dec 2023 | Completed | On track |
P51800030410 Mumbai Suburban · MH | Mumbai Suburban MH | 20 Aug 2021 | 31 Dec 2023 | Completed | 18 mo delay |