L&T Parel Project LLP (JV with ORDPL)

NAME:L&T Parel Project LLP (JV with ORDPL)

Mixed track record

Tracking 6 projects — 6 delivered, 0 still active. 2 of 6 (33%) ran late by an average of 5 months.

Delivery breakdown

How this builder's 6 tracked projects are split by outcome.

4 Delivered on time2 Delivered late

Key numbers

Total projects

6

Active

0

Completed

6

Delayed

2 (33%)

Late or overdue

Avg delay

5 mo

Worst: 18 mo

On-time rate

67%

Of completed projects

Extension rate

33%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (6)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
Crescent Bay - T5
P51900004544
Mumbai City
MH
9 Aug 201731 Aug 2018CompletedOn track
Crescent Bay - T2
P51900010178
Mumbai City
MH
24 Aug 201731 Mar 2019CompletedOn track
Crescent Bay - T3
P51900005188
Mumbai City
MH
10 Aug 201730 Mar 2023Completed12 mo delay
Crescent Bay - T1 - 40, 41 floors
P51900008032
Mumbai City
MH
18 Aug 201731 Mar 2018CompletedOn track
Crescent Bay - T6
P51900004666
Mumbai City
MH
9 Aug 201730 Sept 2019Completed18 mo delay
Crescent Bay - T4
P51900006593
Mumbai City
MH
14 Aug 201731 Aug 2018CompletedOn track