Weak track record

Tracking 3 projects — 0 delivered, 3 still active. 2 of 3 (67%) ran late.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

2 Overdue1 In progress

Key numbers

Total projects

3

Active

3

Completed

0

Delayed

2 (67%)

Late or overdue

Avg delay

On finished projects

On-time rate

Of completed projects

Extension rate

0%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
RERA-GRG-319-2019
Gurgaon · HR
Gurgaon
HR
30 Apr 2023Overdue38 mo overdue
M3M JEWELSame name
RERA-GRG-1199-2022
Gurgaon · HR
Gurgaon
HR
28 Nov 202230 Mar 2026Overdue3 mo overdue
M3M JEWELSame name
RERA-GRG-1336-2023
Gurgaon · HR
Gurgaon
HR
29 May 202329 Mar 2027In progressOn track