Lucina Land Development Limited
RERA delivery track record · complaints · project delays
NAME:LUCINA LAND DEVELOPMENT
B70/100
Good track record
Tracking 8 projects — 4 delivered, 4 still active. 4 of 8 (50%) ran late.
Delivery breakdown
How this builder's 8 tracked projects are split by outcome.
Key numbers
Total projects
8
Active
4
Completed
4
Delayed
4 (50%)
Late or overdue
Avg delay
0 mo
On finished projects
On-time rate
100%
Of completed projects
Extension rate
63%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (8)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P52000001590 Raigarh · MH | Raigarh MH | 29 Jul 2017 | 30 Dec 2020 | Completed | On track |
P52000000709 Raigarh · MH | Raigarh MH | 20 Jul 2017 | 30 Mar 2024 | Overdue | 27 mo overdue |
P52000001160 Raigarh · MH | Raigarh MH | 26 Jul 2017 | 29 Feb 2020 | Completed | On track |
P52000000475 Raigarh · MH | Raigarh MH | 18 Jul 2017 | 30 Jan 2025 | Overdue | 17 mo overdue |
P52000000488 Raigarh · MH | Raigarh MH | 18 Jul 2017 | 30 Dec 2024 | Overdue | 18 mo overdue |
P52000000835 Raigarh · MH | Raigarh MH | 23 Jul 2017 | 30 Jun 2024 | Overdue | 24 mo overdue |
P52000001592 Raigarh · MH | Raigarh MH | 29 Jul 2017 | 30 Jun 2019 | Completed | On track |
P52000002658 Raigarh · MH | Raigarh MH | 2 Aug 2017 | 30 Jun 2021 | Completed | On track |