M/s Keytech
RERA delivery track record · complaints · project delays
NAME:M S KEYTECH
D48/100
Weak track record
Tracking 4 projects — 2 delivered, 2 still active. 1 of 4 (25%) ran late by an average of 8 months.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
2
Completed
2
Delayed
1 (25%)
Late or overdue
Avg delay
7.5 mo
Worst: 15 mo
On-time rate
50%
Of completed projects
Extension rate
50%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800032184 Mumbai Suburban · MH | Mumbai Suburban MH | 14 Dec 2021 | 31 Dec 2024 | Completed | 15 mo delay |
P51800046013 Mumbai Suburban · MH | Mumbai Suburban MH | 15 Jun 2022 | 31 Dec 2025 | Overdue | On track |
P51800052639 Mumbai Suburban · MH | Mumbai Suburban MH | 15 Sept 2023 | 31 Dec 2026 | In progress | On track |
P51800000849 Mumbai Suburban · MH | Mumbai Suburban MH | 23 Jul 2017 | 30 Dec 2026 | Completed | On track |