Strong track record

Tracking 3 projects — 3 delivered, 0 still active. No delays recorded so far.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

3 Delivered on time

Key numbers

Total projects

3

Active

0

Completed

3

Delayed

0 (0%)

Late or overdue

Avg delay

0 mo

On finished projects

On-time rate

100%

Of completed projects

Extension rate

0%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800024086
Mumbai Suburban · MH
Mumbai Suburban
MH
20 Jan 202030 Oct 2023CompletedOn track
P51800023315
Mumbai Suburban · MH
Mumbai Suburban
MH
11 Dec 201930 Oct 2023CompletedOn track
P51800034195
Mumbai Suburban · MH
Mumbai Suburban
MH
25 Mar 202231 Dec 2024CompletedOn track