M/S. SAMBHAV SHELTERS

RERA delivery track record · complaints · project delays

NAME:M S SAMBHAV SHELTERS

Poor track record

Tracking 2 projects — 1 delivered, 1 still active. 1 of 2 (50%) ran late by an average of 18 months. Limited history — read the project list before drawing conclusions.

This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.

Delivery breakdown

How this builder's 2 tracked projects are split by outcome.

1 Delivered late1 In progress

Key numbers

Total projects

2

Active

1

Completed

1

Delayed

1 (50%)

Late or overdue

Avg delay

18 mo

Worst: 18 mo

On-time rate

0%

Of completed projects

Extension rate

50%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (2)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51900003287
Mumbai City · MH
Mumbai City
MH
5 Aug 201730 Jun 2021Completed18 mo delay
P51900034807
Mumbai City · MH
Mumbai City
MH
28 Apr 202230 Dec 2026In progressOn track