MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY
RERA delivery track record · complaints · project delays
NAME:MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY
C57/100
Mixed track record
Tracking 8 projects — 7 delivered, 1 still active. 3 of 8 (38%) ran late by an average of 7 months.
Delivery breakdown
How this builder's 8 tracked projects are split by outcome.
Key numbers
Total projects
8
Active
1
Completed
7
Delayed
3 (38%)
Late or overdue
Avg delay
6.6 mo
Worst: 24 mo
On-time rate
71%
Of completed projects
Extension rate
38%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (8)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800002323 Mumbai Suburban · MH | Mumbai Suburban MH | 31 Jul 2017 | 31 May 2018 | Completed | On track |
P51800008549 Mumbai Suburban · MH | Mumbai Suburban MH | 19 Aug 2017 | 31 Dec 2017 | Completed | On track |
P51800000040 Mumbai Suburban · MH | Mumbai Suburban MH | 16 Jun 2017 | 31 Dec 2019 | Completed | 24 mo delay |
P51800008115 Mumbai Suburban · MH | Mumbai Suburban MH | 18 Aug 2017 | 31 Dec 2017 | Completed | On track |
P51800000017 Mumbai Suburban · MH | Mumbai Suburban MH | 8 Jun 2017 | 31 Dec 2018 | Completed | 22 mo delay |
P51800000019 Mumbai Suburban · MH | Mumbai Suburban MH | 11 Jun 2017 | 30 Dec 2018 | Completed | On track |
Planning, Designing, Constuction and Obtaining Necessary Approvals for 72 HIG t/s on lumpsum Turnkey P51800000041 Mumbai Suburban · MH | Mumbai Suburban MH | 16 Jun 2017 | 30 Jun 2018 | Overdue | 68 mo overdue |
P51800000063 Mumbai Suburban · MH | Mumbai Suburban MH | 22 Jun 2017 | 13 Dec 2018 | Completed | On track |