Mahindra Lifespace Developers limited
RERA delivery track record · complaints · project delays
NAME:MAHINDRA LIFESPACE DEVELOPERS
A86/100
Strong track record
Tracking 16 projects — 12 delivered, 4 still active. 2 of 16 (13%) ran late by an average of 2 months.
Delivery breakdown
How this builder's 16 tracked projects are split by outcome.
Key numbers
Total projects
16
Active
4
Completed
12
Delayed
2 (13%)
Late or overdue
Avg delay
2 mo
Worst: 24 mo
On-time rate
92%
Of completed projects
Extension rate
13%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (16)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P52100000217 Pune · MH | Pune MH | 10 Jul 2017 | 31 Mar 2018 | Completed | On track |
P52100000210 Pune · MH | Pune MH | 10 Jul 2017 | 30 Jun 2018 | Completed | On track |
P52100000281 Pune · MH | Pune MH | 12 Jul 2017 | 30 Jun 2018 | Completed | On track |
P52100000416 Pune · MH | Pune MH | 15 Jul 2017 | 30 Jun 2018 | Completed | On track |
P52100000249 Pune · MH | Pune MH | 10 Jul 2017 | 31 Dec 2018 | Completed | On track |
P52100000171 Pune · MH | Pune MH | 9 Jul 2017 | 30 Dec 2020 | Completed | On track |
P51800016833 Mumbai Suburban · MH | Mumbai Suburban MH | 18 Jun 2018 | 30 Sept 2023 | Completed | On track |
P51800022126 Mumbai Suburban · MH | Mumbai Suburban MH | 28 Aug 2019 | 30 Mar 2025 | Completed | On track |
P51800022067 Mumbai Suburban · MH | Mumbai Suburban MH | 25 Aug 2019 | 30 Mar 2025 | Completed | On track |
P51800028352 Mumbai Suburban · MH | Mumbai Suburban MH | 18 Feb 2021 | 30 Jun 2026 | Overdue | On track |
P51800031699 Mumbai Suburban · MH | Mumbai Suburban MH | 8 Nov 2021 | 31 Dec 2025 | Overdue | 6 mo overdue |
P51800033573 Mumbai Suburban · MH | Mumbai Suburban MH | 22 Feb 2022 | 30 Jun 2026 | Overdue | On track |
P51800033415 Mumbai Suburban · MH | Mumbai Suburban MH | 22 Feb 2022 | 31 Jul 2025 | Completed | On track |
P51800054671 Mumbai Suburban · MH | Mumbai Suburban MH | 2 Feb 2024 | 31 Dec 2029 | In progress | On track |
P51800000242 Mumbai Suburban · MH | Mumbai Suburban MH | 10 Jul 2017 | 31 Oct 2019 | Completed | 24 mo delay |
P52000000461 Raigarh · MH | Raigarh MH | 18 Jul 2017 | 30 Jun 2018 | Completed | On track |