Weak track record

Tracking 3 projects — 0 delivered, 3 still active. 2 of 3 (67%) ran late.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

2 Overdue1 In progress

Key numbers

Total projects

3

Active

3

Completed

0

Delayed

2 (67%)

Late or overdue

Avg delay

On finished projects

On-time rate

Of completed projects

Extension rate

0%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
RERA-PKL-928-2021
Faridabad · HR
Faridabad
HR
15 Apr 2026Overdue2 mo overdue
RERA-PKL-1900-2025
Faridabad · HR
Faridabad
HR
12 Nov 2030In progressOn track
RERA-PKL-954-2021
Faridabad · HR
Faridabad
HR
16 May 2026Overdue1 mo overdue