MANTRA ERECTORS AND BUILDERS LLP

RERA delivery track record · complaints · project delays

NAME:MANTRA ERECTORS AND BUILDERS

Poor track record

Tracking 4 projects — 4 delivered, 0 still active. 3 of 4 (75%) ran late by an average of 14 months.

Delivery breakdown

How this builder's 4 tracked projects are split by outcome.

1 Delivered on time3 Delivered late

Key numbers

Total projects

4

Active

0

Completed

4

Delayed

3 (75%)

Late or overdue

Avg delay

13.5 mo

Worst: 18 mo

On-time rate

25%

Of completed projects

Extension rate

75%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (4)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P52100001377
Pune · MH
Pune
MH
27 Jul 201730 Dec 2020CompletedOn track
P52100002639
Pune · MH
Pune
MH
2 Aug 201730 Jun 2021Completed18 mo delay
P52100001660
Pune · MH
Pune
MH
29 Jul 201730 Jun 2021Completed18 mo delay
P52100001260
Pune · MH
Pune
MH
27 Jul 201730 Jun 2021Completed18 mo delay