Maple City Developers

RERA delivery track record · complaints · project delays

NAME:MAPLE CITY DEVELOPERS

Weak track record

Tracking 3 projects — 0 delivered, 3 still active. 2 of 3 (67%) ran late.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

2 Overdue1 In progress

Key numbers

Total projects

3

Active

3

Completed

0

Delayed

2 (67%)

Late or overdue

Avg delay

On finished projects

On-time rate

Of completed projects

Extension rate

33%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P52100008882
Pune · MH
Pune
MH
19 Aug 201730 Dec 2021Overdue54 mo overdue
P52100007230
Pune · MH
Pune
MH
17 Aug 201730 Dec 2023Overdue30 mo overdue
P52100007009
Pune · MH
Pune
MH
17 Aug 201730 Dec 2022In progressOn track