MARVEL SIGMA HOMES PRIVATE LIMITED
NAME:MARVEL SIGMA HOMES
B73/100
Good track record
Tracking 12 projects — 4 delivered, 8 still active. 7 of 12 (58%) ran late.
Delivery breakdown
How this builder's 12 tracked projects are split by outcome.
Key numbers
Total projects
12
Active
8
Completed
4
Delayed
7 (58%)
Late or overdue
Avg delay
0 mo
On finished projects
On-time rate
100%
Of completed projects
Extension rate
33%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (12)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P52100001878 Pune · MH | Pune MH | 29 Jul 2017 | 30 Dec 2022 | Overdue | 42 mo overdue |
P52100010211 Pune · MH | Pune MH | 24 Aug 2017 | 30 Dec 2021 | Overdue | 54 mo overdue |
P52100001711 Pune · MH | Pune MH | 29 Jul 2017 | 31 Dec 2019 | In progress | On track |
P52100006134 Pune · MH | Pune MH | 14 Aug 2017 | 30 Jun 2018 | Completed | On track |
P52100003507 Pune · MH | Pune MH | 5 Aug 2017 | 31 Oct 2018 | Overdue | 80 mo overdue |
P52100002242 Pune · MH | Pune MH | 31 Jul 2017 | 31 Dec 2018 | Overdue | 50 mo overdue |
P52100002438 Pune · MH | Pune MH | 1 Aug 2017 | 30 Jun 2022 | Overdue | 48 mo overdue |
P52100006797 Pune · MH | Pune MH | 16 Aug 2017 | 31 Dec 2019 | Overdue | 11 mo overdue |
P52100007453 Pune · MH | Pune MH | 17 Aug 2017 | 31 Dec 2019 | Completed | On track |
P52100010835 Pune · MH | Pune MH | 31 Aug 2017 | 30 Dec 2022 | Overdue | 42 mo overdue |
P52100008708 Pune · MH | Pune MH | 19 Aug 2017 | 31 Dec 2018 | Completed | On track |
P52100007022 Pune · MH | Pune MH | 17 Aug 2017 | 31 Dec 2018 | Completed | On track |