MILAN INTERBUILT PRIVATE LIMITED
RERA delivery track record · complaints · project delays
NAME:MILAN INTERBUILT
F24/100
Poor track record
Tracking 5 projects — 3 delivered, 2 still active. 3 of 5 (60%) ran late by an average of 6 months.
Delivery breakdown
How this builder's 5 tracked projects are split by outcome.
Key numbers
Total projects
5
Active
2
Completed
3
Delayed
3 (60%)
Late or overdue
Avg delay
6 mo
Worst: 12 mo
On-time rate
33%
Of completed projects
Extension rate
80%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (5)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800003357 Mumbai Suburban · MH | Mumbai Suburban MH | 5 Aug 2017 | 31 Mar 2018 | Completed | On track |
P51800008647 Mumbai Suburban · MH | Mumbai Suburban MH | 19 Aug 2017 | 31 Mar 2018 | Completed | 12 mo delay |
P51800018586 Mumbai Suburban · MH | Mumbai Suburban MH | 21 Nov 2018 | 30 Jun 2021 | Overdue | 39 mo overdue |
P51800032172 Mumbai Suburban · MH | Mumbai Suburban MH | 14 Dec 2021 | 31 Dec 2024 | Overdue | On track |
P51800046482 Mumbai Suburban · MH | Mumbai Suburban MH | 5 Aug 2022 | 28 Feb 2025 | Completed | 6 mo delay |