MOHAN LIFESPACES LLP

RERA delivery track record · complaints · project delays

NAME:MOHAN LIFESPACES

Poor track record

Tracking 4 projects — 4 delivered, 0 still active. 4 of 4 (100%) ran late by an average of 28 months.

Delivery breakdown

How this builder's 4 tracked projects are split by outcome.

4 Delivered late

Key numbers

Total projects

4

Active

0

Completed

4

Delayed

4 (100%)

Late or overdue

Avg delay

28.5 mo

Worst: 48 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (4)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51700000829
Thane · MH
Thane
MH
23 Jul 201731 Dec 2019Completed36 mo delay
P51700002244
Thane · MH
Thane
MH
31 Jul 201730 Jun 2019Completed18 mo delay
P51700002731
Thane · MH
Thane
MH
4 Aug 201730 Jun 2018Completed12 mo delay
P51700007011
Thane · MH
Thane
MH
17 Aug 201731 Dec 2019Completed48 mo delay