Mont Vert Elegance
NAME:MONT VERT ELEGANCE
F0/100
Poor track record
Tracking 3 projects — 2 delivered, 1 still active. 3 of 3 (100%) ran late by an average of 39 months.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
1
Completed
2
Delayed
3 (100%)
Late or overdue
Avg delay
39 mo
Worst: 42 mo
On-time rate
0%
Of completed projects
Extension rate
67%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P52100007210 Pune · MH | Pune MH | 17 Aug 2017 | 30 Dec 2022 | Overdue | 42 mo overdue |
P52100002756 Pune · MH | Pune MH | 4 Aug 2017 | 31 Dec 2018 | Completed | 36 mo delay |
P52100002449 Pune · MH | Pune MH | 1 Aug 2017 | 31 Dec 2018 | Completed | 42 mo delay |