Mumbai Shelter Housing Development

RERA delivery track record · complaints · project delays

NAME:MUMBAI SHELTER HOUSING DEVELOPMENT

Mixed track record

Tracking 3 projects — 1 delivered, 2 still active. 2 of 3 (67%) ran late.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

1 Delivered on time2 Overdue

Key numbers

Total projects

3

Active

2

Completed

1

Delayed

2 (67%)

Late or overdue

Avg delay

0 mo

On finished projects

On-time rate

100%

Of completed projects

Extension rate

67%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800008871
Mumbai Suburban · MH
Mumbai Suburban
MH
19 Aug 201731 Jul 2019Overdue41 mo overdue
P51800010246
Mumbai Suburban · MH
Mumbai Suburban
MH
24 Aug 201731 Dec 2019Overdue36 mo overdue
P51800001120
Mumbai City · MH
Mumbai City
MH
26 Jul 201730 Jun 2018CompletedOn track