NANDAN ASSOCIATES
NAME:NANDAN ASSOCIATES
C55/100
Mixed track record
Tracking 3 projects — 3 delivered, 0 still active. 1 of 3 (33%) ran late by an average of 8 months.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
0
Completed
3
Delayed
1 (33%)
Late or overdue
Avg delay
8 mo
Worst: 24 mo
On-time rate
67%
Of completed projects
Extension rate
33%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P52100000563 Pune · MH | Pune MH | 18 Jul 2017 | 30 Mar 2022 | Completed | On track |
P52100000883 Pune · MH | Pune MH | 23 Jul 2017 | 31 Mar 2018 | Completed | On track |
P52100001376 Pune · MH | Pune MH | 27 Jul 2017 | 30 Mar 2022 | Completed | 24 mo delay |