Weak track record
Tracking 2 projects — 0 delivered, 2 still active. 1 of 2 (50%) ran late. Limited history — read the project list before drawing conclusions.
This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.
Delivery breakdown
How this builder's 2 tracked projects are split by outcome.
Key numbers
Total projects
2
Active
2
Completed
0
Delayed
1 (50%)
Late or overdue
Avg delay
—
On finished projects
On-time rate
—
Of completed projects
Extension rate
100%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (2)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| NEO AMITY P51900008285 | Mumbai City MH | 18 Aug 2017 | 30 Dec 2023 | In progress | On track |
| NEO ORNATE P51900009675 | Mumbai City MH | 22 Aug 2017 | 30 Dec 2022 | Overdue | 30 mo overdue |