NEEPA REAL ESTATES PRIVATE LIMITED
NAME:NEEPA REAL ESTATES
A94/100
Strong track record
Tracking 6 projects — 4 delivered, 2 still active. 1 of 6 (17%) ran late.
Delivery breakdown
How this builder's 6 tracked projects are split by outcome.
Key numbers
Total projects
6
Active
2
Completed
4
Delayed
1 (17%)
Late or overdue
Avg delay
0 mo
On finished projects
On-time rate
100%
Of completed projects
Extension rate
0%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (6)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800015981 Mumbai Suburban · MH | Mumbai Suburban MH | 10 Apr 2018 | 30 Dec 2021 | Completed | On track |
P51800015556 Mumbai Suburban · MH | Mumbai Suburban MH | 8 Mar 2018 | 30 Dec 2022 | Completed | On track |
P51800017139 Mumbai Suburban · MH | Mumbai Suburban MH | 16 Jul 2018 | 30 Dec 2023 | Completed | On track |
P51800028025 Mumbai Suburban · MH | Mumbai Suburban MH | 26 Jan 2021 | 30 Jun 2023 | Overdue | 36 mo overdue |
P51800029408 Mumbai Suburban · MH | Mumbai Suburban MH | 29 May 2021 | 30 Dec 2023 | Completed | On track |
P51800032286 Mumbai Suburban · MH | Mumbai Suburban MH | 22 Dec 2021 | 31 Dec 2026 | In progress | On track |