NIRBAN INFRASTRUCTURE PVT LTD

NAME:NIRBAN INFRASTRUCTURE PVT LTD

Poor track record

Tracking 2 projects — 1 delivered, 1 still active. 2 of 2 (100%) ran late by an average of 12 months. Limited history — read the project list before drawing conclusions.

This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.

Delivery breakdown

How this builder's 2 tracked projects are split by outcome.

1 Delivered late1 Overdue

Key numbers

Total projects

2

Active

1

Completed

1

Delayed

2 (100%)

Late or overdue

Avg delay

12 mo

Worst: 12 mo

On-time rate

0%

Of completed projects

Extension rate

50%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (2)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
BISMILLAH ELITE
P51900031646
Mumbai City
MH
3 Nov 202131 Dec 2024Overdue18 mo overdue
BISMILLAH RESIDENCY
P51900008056
Mumbai City
MH
18 Aug 201731 Jul 2018Completed12 mo delay