Navkar Infra Projects

NAME:Navkar Infra Projects

Poor track record

Tracking 5 projects — 2 delivered, 3 still active. 4 of 5 (80%) ran late by an average of 9 months.

Delivery breakdown

How this builder's 5 tracked projects are split by outcome.

1 Delivered on time1 Delivered late3 Overdue

Key numbers

Total projects

5

Active

3

Completed

2

Delayed

4 (80%)

Late or overdue

Avg delay

9 mo

Worst: 18 mo

On-time rate

50%

Of completed projects

Extension rate

80%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (5)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
NAVKAR PARADISE
P51800000715
Mumbai Suburban
MH
23 Jul 201715 Jun 2021Overdue42 mo overdue
SHANTI VIJAY
P51800000790
Mumbai Suburban
MH
23 Jul 201710 Jul 2019CompletedOn track
SAJAG CHS
P51800001223
Mumbai Suburban
MH
27 Jul 201724 Jun 2019Completed18 mo delay
YELLOW ROSES
P51800000712
Mumbai Suburban
MH
20 Jul 201719 Jul 2020Overdue18 mo overdue
SAKSHAT NAVKAR
P51800000503
Mumbai Suburban
MH
18 Jul 201730 Sept 2019Overdue13 mo overdue