OASIS LANDMARKS LLP
NAME:OASIS LANDMARKS
D40/100
Weak track record
Tracking 4 projects — 0 delivered, 4 still active. 3 of 4 (75%) ran late.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
4
Completed
0
Delayed
3 (75%)
Late or overdue
Avg delay
—
On finished projects
On-time rate
—
Of completed projects
Extension rate
0%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
RERA-GRG-421-2019 Gurgaon · HR | Gurgaon HR | 12 Aug 2017 | 31 Dec 2020 | Overdue | 66 mo overdue |
RERA-GRG-991-2021 Gurgaon · HR | Gurgaon HR | 17 Aug 2017 | 30 Apr 2020 | Overdue | 74 mo overdue |
RERA-GRG-1224-2022 Gurgaon · HR | Gurgaon HR | 16 Jan 2023 | 31 Dec 2029 | In progress | On track |
RERA-GRG-628-2020 Gurgaon · HR | Gurgaon HR | 17 Aug 2017 | 30 Sept 2019 | Overdue | 81 mo overdue |