PARDIS CONSTRUCTION LLP
RERA delivery track record · complaints · project delays
NAME:PARDIS CONSTRUCTION
C55/100
Mixed track record
Tracking 3 projects — 3 delivered, 0 still active. 1 of 3 (33%) ran late by an average of 8 months.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
0
Completed
3
Delayed
1 (33%)
Late or overdue
Avg delay
8 mo
Worst: 24 mo
On-time rate
67%
Of completed projects
Extension rate
33%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800003603 Mumbai Suburban · MH | Mumbai Suburban MH | 5 Aug 2017 | 30 Sept 2020 | Completed | 24 mo delay |
P51800011608 Mumbai Suburban · MH | Mumbai Suburban MH | 31 Aug 2017 | 31 Mar 2018 | Completed | On track |
P51800028172 Mumbai Suburban · MH | Mumbai Suburban MH | 10 Feb 2021 | 22 Apr 2024 | Completed | On track |